Delays in implementation of projects of size are of national concern. The Aditya Birla Group s flagship Hindalco Industries is simultaneously executing five new projects, three smelters and two alumina refineries.
All are located in remote parts, where bauxite and coal are found. On their completion, the company will have annual alumina refining capacity of six mt and aluminium smelting capacity of 1.7 mt.
The country will need all this extra aluminium from Hindalco and whatever the growth plans of National Aluminium Company and Vedanta would generate.
This is because demand for the metal will continue to grow at a double digit rate for many years.
In this context, Hindalco recently said: Of late, uncertainty in the regulatory environment has impacted the progress of some of the greenfield projects and it has posed challenges with respect to their commissioning on schedule.
All these projects are located in remote areas, devoid of adequate infrastructure...Project execution also gets impacted by local factors.
For Hindalco, generally not given to complaining, to say all this is likely to make the government sit up and take corrective steps.
What Hindalco is experiencing holds good for industry in general.
The immediate trigger for Hindalco s complaint is delay in securing forest clearances for opening mines in the Mahan coal block in Madhya Pradesh.
Fuel for the 1,000 Mw captive power plant of the 359,000-tonne smelter of the Mahan Aluminium project is to be drawn from Mahan coal mines, to be run as an equally owned joint venture between Hindalco and Essar.
Click NEXT to read more...
Delays in implementation of projects of size are of national concern.
this
Users
Comment
article